Skip to article

Tasks Panel and Views

The Gantt View

Draft guidance · pending workflow review

Summary: Review scheduled work, dates, and dependencies in a Program workspace.

Choose Gantt in a Program workspace to review work against dates. The standard Tasks header exposes Tree, Board, and Table in other workspace contexts; Gantt is conditional on Program view.

Prepare the view

Select the relevant Program and project. Check task scheduling, start and end dates, and active filters. Unscheduled backlog items do not become booked appointments simply because you open a chart.

Use the available scale and navigation controls to examine the period you need. Open a task to inspect its dates and Dependencies tab before changing its plan.

Separate three planning questions

Use Schedule, Reschedule, or the task's Time tab to inspect and manage appointments. The Gantt chart is not a replacement for those staffing details.

Check changes

Date and dependency changes can affect linked work. Review the task and its successors after an edit, and resolve any workflow or permission message before continuing. Do not infer a fixed delivery commitment from a bar alone; check scope, staffing, and the team's current agreement.

If a task is absent, inspect the selected Program, project, dates, scheduled status, stages, and visible states. Changing the chart scale cannot reveal work excluded by those filters.